Mall Road Closed for Resurfacing

Florence Mayor Steve Holt and City Engineer Bill Batson are pleased to notify the public that work on Mall Road began last week. Signs have been placed on the roadway to designate the construction area.

Mayor Holt said the project is an important part of the city’s street development for the year and includes a traffic light at the intersection of Mall Road and Hough Road.

According to the city, Mall Road will be paved in four phases.  Crews will complete one phase before beginning another to allow for detoured traffic.  Businesses will be open during construction, and signs will be placed to detour traffic.

The contractor will need three consecutive dry days to make progress on paving. Depending upon weather conditions throughout the project, the completion time for each phase is as follows: two weeks for the first phase, one week for the second phase, one day for the third phase, and two weeks for the fourth phase.

The sections include:

  • Mall Road      from Florence Boulevard to Cloyd Boulevard
  • Mall Road      from Cloyd Boulevard to N. Mall Court
  • Mall Road      from N. Mall Court to Cox Creek Parkway
  • Hough Road   from Mall Road to Cox Creek Parkway

If you have any questions regarding the re-surfacing project, please contact the Engineering Office at 256-760-6350.